How does purchasing work in CUED?

Purchasing is done through a system called the Engineering Department Requisitioning System, or EDRS for short. It is accessible only to some staff and graduate students, with no exceptions. This system offers access to the university-wide purchasing system known as the Marketplace,as well as to a long list of other companies that are “on the system”.

If you want to buy something, the first step is to decide what you want, and then find a supplier to sell it to you. This is done in the usual way, via a search engine of your choice. It’s best to look for big, well known national suppliers, or suppliers local to Cambridge.

Once you have selected your product and supplier, you try them in the system. First try the marketplace route, which is by far the easier option if it is possible. If you are able to find the product on marketplace, then it doesn’t matter which supplier it’s from, and the order will go through without issue. Most marketplace suppliers deliver within the next two working days.

If you cannot find the product on marketplace, then search the list of companies that are “on the system” for your desired supplier. If yours is not on the list, try and find a different supplier that is. If you cannot find a supplier on the system for your desired product, you must choose a different product. Table 1 shows a list of commonly used suppliers that have well-indexed websites.

Table 1: A list of commonly used suppliers.
Supplier Typical Items Notes
RS Hardware e.g. Screws,
Motors, Switches etc.
On Marketplace
Farnell Discrete electronic
components e.g. ICs,
Resistors etc.
On Marketplace
Comar Low-Cost optics e.g.
Lenses, Filters, Gratings
Not on Marketplace
Thor High end optics On Marketplace
Sigma Chemical supplies On Marketplace
CUED Stores Various metal stock e.g.
Sheet, Bar and Round
Catalogue Online on Dyson
Centre Page

Once an appropriate supplier has been found, they must be contacted for a quote to supply the desired product. This can then be entered into the system and the order will be processed, though non-marketplace suppliers will often take longer to supply than marketplace ones. This lag, coupled with the delay that typically results from having to procure a quote, means that non-marketplace orders typically take as long as one working week to process.

How do students purchase for their projects?

As undergraduates are not permitted to access EDRS, they must work with someone who does have access. Different people will have different preferences on how they want this to happen, but it is always best to have a list of the products you want to buy in advance of contacting them. If possible, have either a product code or directions to information from a supplier, as this will make the process much quicker. Once the order has been placed, the person that placed the order will be notified by email when it arrives. They may instruct you to collect it from Stores (next to the workshops), where you will need the Purchase Order number, and you will be asked to sign to show you have accepted the order.

Are there any ways of getting things which aren't on EDRS?

In broad, yes, though they are not easy. It is usually better to find an alternative product than to try to purchase one that cannot be found on the system. Contact your project leader, supervisor or demonstrator if no alternatives can be found.