Projects run over a 4-week period after the Part IIA examinations, so that undergraduates have no other scheduled activities. Important dates and deadlines are:
| Language projects information session |
Thursday 27 November 12:45, CLIC 2
|
(end of Michaelmas) |
| Project descriptions available for browsing | Monday 1 December | (Michaelmas, week 8) |
| Start of input of preferences (all students) | Monday 19 January | (Week before Lent) |
| Deadline for input of preferences (all students) | by end of Thursday 29 January | (Lent, week 2) |
|
Project allocations (first list) published Project allocations (final list) published |
Thursday 5 February Thursday 12 February |
(Lent, week 3) (Lent, week 4) |
| Preparatory sessions for Lent-start projects | See Project descriptions | (Lent, weeks 5-8) |
| Easter Term project period begins (Language projects: Wednesday 13 May) | Thursday 14 May | (Easter, week 3) |
| Each project will have interim reports or presentations. Deadlines for these vary - see the Project descriptions for details | (Easter, weeks 3-6) | |
| Hand-in date for final report: Multidisciplinary Design project | Friday 5 June | (Easter, week 6) |
| Latest hand-in dates for final reports: all other projects | Thursday 11 June / Friday 12 June | (Easter, week 7) |
Final project reports must be handed in by 4pm on the relevant days. Students should aim to submit ahead of the deadline.
NB: Please refer to the guidance below on allowances for missed sessions, and the policy on deadline extensions for IIA project reports. Project leaders are required to complete all marking by Wednesday week 7 Easter term. In the unlikely event that your project requires hard copy submissions, in that case all interim reports must be resubmitted, appended to your final report.
Last updated on 11/06/2026 18:12